Unbilled extras are not lost at the invoice. They are lost in the four seconds before you say sure. The four things a change order has to carry, three ways to price one, the text message that works from the driveway, and why a commercial directive is a different instrument entirely.
The homeowner catches you on the way to the truck. While you’re here — could you move the outlet to the other wall, and do something about that soffit?
You say sure. It is twenty minutes and a bit of wire. Six weeks later the invoice goes over by $1,800, and the conversation you are now having is not about the soffit. It is about whether anybody ever agreed to pay for it.
That money was not lost at the invoice. It was lost in the driveway, in the four seconds before you said sure.
A change order is not a form. It is a decision, made before the extra work begins, about four things: what the work is, what it costs, what it does to the schedule, and who has agreed to it.
Once the work is finished, all four become arguable. The customer remembers a favor; you remember a job. Neither of you is lying, and there is no document that settles it. The whole value of the paperwork is that it exists before the disagreement, when the customer still wants something from you and is inclined to be reasonable about what it costs.
Contractors skip it for a decent reason: stopping to write something up feels like distrust, and the amounts are small individually. The problem is that they are not small in aggregate. A handful of unbilled extras across a season is a month’s profit. It always lands on the jobs where the relationship was best, because those are the jobs where nobody wanted to be awkward.

Whatever format you use, it has to carry all four. Miss one and you are back to arguing about it later.
The pricing method is a risk decision, not an accounting preference.
A lump sum suits work you can see the end of. You carry the risk of it taking longer than you thought, and in exchange the customer gets certainty and you keep the upside if it goes well.
Unit prices suit work where the quantity is unknown but the rate is not — another twelve feet of trenching, another four fixtures. Agree the rate once and the quantity settles itself.
Time and materials suits work nobody can scope yet, which is most of what comes out of opening up an old building. It is also the method customers like least, so it works better with a not-to-exceed figure attached: T&M up to a ceiling, and we talk again before we pass it.
Whichever you use, price the change on the same basis as the original job. Pricing a change off the top of your head, against an original quote you built properly, is how a profitable job quietly becomes an average one. If you have a rate you built from your actual costs, use it here too.
Most change orders start as a conversation, and that is fine. What matters is what happens in the next hour.
Send the customer a short written confirmation of what you agreed, before the work starts. It does not need a letterhead. It needs the four elements and a request to reply confirming. Three lines sent from the driveway beat a beautifully formatted document sent after the fact:
“Confirming what we agreed just now: relocate the kitchen outlet to the east wall and re-fix the soffit over the back door. $420 plus tax, added to the final invoice. No change to the finish date. Reply yes and I’ll get it done today.”
That is a change order. It has scope, price, schedule and a request for authorization, and if the customer replies “yes”, you have the authorization in writing from the person who owes you the money.
Many written contracts say changes are only valid if made in writing and signed. Where such a clause exists, work done on a handshake is not automatically unrecoverable. But recovering it means arguing about it, and arguing about it is the thing you were trying to avoid. Treat the clause as telling you what the paperwork has to look like, not as a reason to give up on the money.
If you work under standard industry contract forms, there are two different instruments and they behave very differently.
A change order is an agreed amendment. It records the change in the work, the change in the contract sum and the change in the contract time, and it is signed by the owner, the contractor and the architect. All three elements and all three signatures, or it is not a change order.
A construction change directive is the owner telling you to proceed before anyone has agreed the price and time. You generally have to get on with it while the parties work out the cost and schedule impacts, and they convert it to a change order once they settle.
The practical consequence is worth knowing in advance. On that kind of job, “we haven’t agreed a price yet” is not a reason to stop. Your protection is contemporaneous records rather than a signature. Keep daily labor hours, materials and photographs specific to the directed work, separate from the base contract. That file is what you will argue the price from.
Two downstream effects are worth planning for.
Approved changes should flow into your progress billing as their own line, rather than disappearing into the next draw. Bury a change inside a percentage-complete number and it goes invisible, and invisible work draws questions at the end, when you have the least leverage and the customer has the most.
And a mechanics lien is only as good as the underlying entitlement. Lien statutes are state law and differ in detail. The common thread is that they secure what you were entitled to be paid. Extra work with no authorization behind it is exactly the part a payer will contest, and a lien does not manufacture agreement that was never there. The paperwork you did not want to do on the driveway is the paperwork the lien would have relied on.
You do not need a contracts department. You need a rule you actually follow: no extra work starts until the scope, the price, the schedule effect and a yes are in writing somewhere you can find again.
For most small jobs that is a text message sent before you pick the tools back up. For anything bigger it is a one-page form you reuse. The format is not what makes it work. Doing it before the work, instead of after the invoice, is what makes it work.
ON THE FOUR SECONDS IN THE DRIVEWAY
If it takes five minutes to write up, it gets skipped. If it takes forty seconds, it gets done.
The reason extras go unbilled is almost never that the contractor did not know to write them down. It is that writing them down meant finding a laptop later. SendWork puts the quote, the change and the customer’s approval on the phone already in your hand, attached to the job, so the confirmation goes out before you pick the tools back up.