Late Payment Interest: What You Can Add When a Business Customer Pays Late

A business customer who pays late owes you statutory interest at 11.75% a year and £40, £70 or £100 in compensation, whether or not your terms mention it. When an invoice is legally late, how to work out the figure, how to claim it, and what the Commercial Payments Bill would change.

11.75% a year. That is the late payment interest a UK tradesperson can add to an invoice a business customer has paid late. It applies to any debt that falls late between 1 July and 31 December 2026. On top of it sits a fixed compensation sum of £40, £70 or £100, depending on the size of the debt. Neither needs a clause in your terms. Both come from the Late Payment of Commercial Debts (Interest) Act 1998, which has applied to business-to-business invoices since that year. It is a legal right, not a scheme any agency runs for you, and whether you claim it is up to you.

So when the main contractor who owes you for second fix is three weeks past your terms, or a letting agent is still “processing” the boiler replacement, you have more than a polite chaser to work with. Below: who can charge late payment interest, and when an invoice is legally late. Then the arithmetic, how to claim it without burning the relationship, and what the Commercial Payments Bill now going through Parliament would change.

Business customers only, never householders

The Late Payment of Commercial Debts (Interest) Act 1998 applies where the buyer and the supplier are “each acting in the course of a business”. A main contractor, a developer, a landlord’s company, a shop fitting out its premises: all covered. A homeowner paying for a new bathroom is not, however long they take to pay.

That line matters for most trades, because the same week can hold both kinds of job. Before an invoice goes out, know which of your customers the Act protects you against. It is worth saying so on the quote, too.

When an invoice becomes late

If you agreed a payment date, the invoice is late the day after it. Between businesses, GOV.UK’s guidance says agreed terms are normally up to 60 days. Longer terms are allowed only where they are not “grossly unfair” to the supplier. A public authority has 30 days.

If nothing was agreed, section 4 of the Act sets the date for you: 30 days after the customer receives the invoice or 30 days after you do the work, whichever is later. A job finished on the 3rd and invoiced on the 10th becomes late 30 days after the invoice arrives, not after the last day on site.

This is why the invoice date is worth more than it looks. Where no date was agreed, the clock does not start until the invoice is in the customer’s hands, so an invoice left until the weekend is most of a week of interest you cannot claim. Invoicing from site the day the work is done, as the guide to getting paid faster sets out for plumbers, starts the 30 days a week earlier.

Working out the 11.75%

Statutory interest is 8% above the Bank of England’s Bank Rate. It is not the rate on the day you claim, though. The reference rate is fixed twice a year. For interest that starts running between 1 July and 31 December, it is the Bank Rate in force on 30 June. For interest starting between 1 January and 30 June, it is the rate on 31 December.

Bank Rate was 3.75% on 30 June 2026, which sets the rate for this half-year; the Monetary Policy Committee raised it to 4% on 5 November 2026, which does not change the rate on invoices that fall late before 1 January. That gives 8% plus 3.75%, or 11.75% a year, for any invoice that falls late between now and the end of December. The rate stays with that debt until it is paid, even if Bank Rate moves later. An invoice that becomes late in January picks up whatever Bank Rate is on 31 December.

The interest is simple, not compound, and you work it out by the day. An illustration, not a real account:

  • The invoice: £8,400 for a rewire on a commercial unit, on 30-day terms, paid 45 days after it fell due.
  • A year’s interest: £8,400 × 11.75% = £987.00.
  • A day’s interest: £987.00 ÷ 365 = £2.70.
  • 45 days late: £2.70 × 45 = £121.68, plus the fixed compensation of £70 below: £191.68 on top of the invoice.

None of that will change your year. What it does is give the customer a reason to put your invoice ahead of the one from a supplier who never mentions it.

The fixed compensation on top

Section 5A adds a fixed sum for each late invoice, on top of the interest:

  • £40 where the debt is under £1,000
  • £70 where it is £1,000 or more but under £10,000
  • £100 where it is £10,000 or more

If chasing the debt costs you more than that, for example a solicitor’s letter or a collection fee, the Act lets you claim the reasonable extra costs as well.

Owner of a small plumbing firm types a letter at a kitchen table with an invoice and calculator
The claim is a letter, not a court form: the invoice, the days late, the daily rate and the fixed sum, set out once.

When your own terms replace the statute

You can agree a different late-payment rate in the contract, and many trade terms do. According to GOV.UK, you cannot then claim statutory interest on top: the contract rate applies instead. Section 8 allows that only where the contract gives a “substantial remedy” for late payment. A term that offers less is void to that extent, and statutory interest applies after all.

That makes it worth reading your own standard terms, and the ones a main contractor asks you to sign, for a clause that quietly swaps 11.75% for something smaller. If your quote says nothing about interest, the statute fills the gap.

Claiming late payment interest without losing the customer

Most of the time, the right is more useful as a reason to pay on time than as money you collect. The path runs like this:

  1. On the quote and the invoice: the payment date, and one line saying that late payment carries interest and compensation under the Late Payment of Commercial Debts (Interest) Act 1998. Putting the price in writing before the job starts matters for the same reason: a figure the customer agreed to is harder to dispute.
  2. A few days after the due date: a reminder that restates the amount and the date it fell due, and notes that interest is now running. Many customers pay here.
  3. If it is still unpaid: a letter setting out the invoice, the days late, the daily rate, the interest to date and the fixed sum, with a date to pay by.
  4. If that date passes: the interest and compensation can be included in a claim through the courts alongside the debt. Take advice before you start one, especially on larger sums.

Whether to go past step two is a judgement about the customer. A developer who pays every invoice six weeks late is costing you money you can put a figure on. A long-standing customer who slipped once may be worth a phone call instead. The Act gives you the right; it does not oblige you to use it every time.

What the Commercial Payments Bill would change

The government’s Commercial Payments Bill would go further. Its factsheet describes these measures:

  • A cap of 60 days on payment terms, with limited exemptions.
  • Interest at 8% over base made mandatory, rather than something a contract can replace.
  • A ban on deducting and withholding retentions under construction contracts, with the timing still to be consulted on.
  • New powers for the Small Business Commissioner to investigate, adjudicate and fine persistent late payers.

The retention ban is the part builders and subcontractors will notice most. It is also furthest off, because its timing has not been set.

None of this is law yet. The Bill completed its Lords stages on 20 October 2026 and had its first reading in the House of Commons on 21 October 2026, with second reading still to be scheduled and the rest of the Commons stages still to come. The government says there will be a lead-in period and that the measures will not apply retrospectively. Until it passes and a start date is set, keep your retentions and payment terms under your current contracts and the 1998 Act.

The rule for your next late invoice

If the customer is a business and your invoice is past its agreed date, or 30 days after it arrived with no date agreed, interest is running at 11.75% a year on anything that fell late this half-year, and £40, £70 or £100 in compensation is already owed. Put the figure in your next reminder. Whether you ever collect it is your call. Knowing it is there changes the conversation.

WHEN THE CLOCK STARTS

An invoice sent from the van is a week less waiting for your money.

Statutory interest only runs from the date the invoice reaches the customer, so the days between finishing and invoicing are days nobody owes you for. SendWork keeps the quote, the job and the invoice together on your phone, so the invoice can go out the day the work is done.