Builder talks over the garden wall with a neighbour behind terraced houses with scaffolding

Party Wall Notices: What Has to Be Served Before the Loft or Extension Starts

A loft conversion, rear extension or chimney-breast removal on a terrace usually needs a party wall notice, served by your client one or two months before work starts. Which notice the job needs, what it must say, what fourteen days of silence triggers, and how to give a start date that holds.

Suppose a couple accept your quote in mid-October for a loft conversion on their Victorian mid-terrace. The steels will bear into both party walls, and the chimney breast on one side is coming out. They want you on site in the first week of January. Whether that date holds has little to do with your diary. It depends on two neighbours, a two-month notice period and fourteen days of their silence.

That is the Party Wall etc. Act 1996. In England and Wales it governs work on party walls, new walls on the boundary and digging near a neighbour’s foundations. It gives your client the right to do this work. It gives the neighbours notice, time and, if they want one, a surveyor. Each of those can move a start date. Serving the notice is a legal duty on your client, not a courtesy. So if you build lofts and extensions in England and Wales, the time to think about party wall notices is the moment you give a client a start date: which notice the job needs, how far ahead it must go, what it says, and what happens when the neighbour does not reply.

The duty is the client’s; the programme is yours

The Act puts the obligation on the building owner. Section 3(1) says that before exercising the rights in section 2, “a building owner shall serve on any adjoining owner a notice”. Section 20 defines the building owner as the owner of land “who is desirous of exercising rights under this Act”. That is your client, not you. On a home job your client is already the domestic client under the CDM Regulations. Under this Act they are also the building owner.

It may well be you who spots that a notice is needed, and the government’s explanatory booklet allows for that: it talks about the notice given by “you (or your professional adviser on your behalf)”. It also names builders directly, warning neighbours about “a builder carrying out work on your neighbour’s behalf” who starts without notice. If you serve for the client, the notice is still the client’s, in the client’s name. So the question to settle at the quote is not whose duty it is but who is making sure the notice goes out in time. Agree that with the client, so neither of you assumes the other has done it.

Which party wall notice the job needs

The Act has three kinds of notice, and one job can need more than one.

  • A new wall on the boundary (section 1). A new wall astride the line of junction needs notice “at least one month before” the work starts. So does one built wholly on your client’s side of it.
  • Work to an existing party wall (sections 2 and 3). This is the party structure notice, served “at least two months before the date on which the proposed work will begin”. Section 2 covers underpinning, thickening or raising a party structure, cutting into it “for any purpose” and cutting away a projecting chimney breast. The booklet’s examples include cutting in “to take the bearing of a beam (for example for a loft conversion)” and adding another storey.
  • Digging near the neighbour’s foundations (section 6). Excavation within three metres needs notice if it goes deeper than the bottom of the neighbour’s foundations. Within six metres, it needs notice if it would cut a 45-degree line drawn down from them. The notice goes “at least one month before beginning to excavate”. A rear extension whose footings go deeper than next door’s can fall here.

The loft in the example needs a party structure notice on each side, two months ahead. A single-storey rear extension on a semi might need a section 6 notice to one neighbour and nothing to the other. Work starts earlier than the notice period allows only if the neighbour “agrees, in writing”.

What the notice has to say

There is no official form, so if you are drafting the notice for the client, section 3(1) is your checklist. It requires three things in a party structure notice, and the third is the start date you are about to quote:

  1. the building owner’s name and address;
  2. details of the proposed work, its “nature and particulars”, with plans, sections and details where special foundations are proposed; and
  3. the date on which the proposed work will begin.

An excavation notice under section 6 must come with plans and sections showing the site and depth of the excavation. The booklet adds that joint owners must all be named. Email is allowed only where the neighbour has said they are willing to receive the notice that way. A party structure or excavation notice lapses if the work has not begun within twelve months of service. A notice served too early for a job that then slips can expire. That cuts both ways for your diary: serve too late and the start moves; serve too early on a job that keeps slipping and the notice may need serving again.

Builder hands an envelope to a neighbour at the front door of a terraced house
Serve the notice on a date you can prove, and the clock starts cleanly.

Fourteen days of silence is a dispute

This is the rule that can decide a start date. Under section 5, if a neighbour “does not serve a notice indicating his consent to it within the period of fourteen days”, the Act treats them as having refused. In the Act’s words, “a dispute shall be deemed to have arisen”. Section 6(7) says the same for excavation notices. A neighbour who ignores the letter has not consented; they have started the dispute procedure. The new-wall notice is the exception. Under section 1(4), silence there means your client may only build the wall wholly on their own land, at their own expense.

A dispute goes to surveyors under section 10. Either both owners agree one surveyor, or each appoints their own and the two select a third. If the neighbour refuses to appoint, or does nothing for ten days after a request, your client can appoint on their behalf. The surveyors make an award setting out the work, how it is to be done and the condition of the neighbour’s property. Once made, the award is conclusive, and either side can appeal to the county court within fourteen days of receiving it.

For your programme, this is the stretch you do not control. Once a neighbour goes quiet, the start date follows the surveyors’ timetable, and that is worth telling the client at the quote rather than later.

On who usually pays, the booklet is plain: “the Building Owner will pay all costs associated with drawing up the award including the adjoining owner’s surveyor’s fees, if the works are solely for the Building Owner’s benefit.” That cost belongs in your client’s budget conversation, not in your price.

The loft, dated

Back to the example, with the notices served on Monday 19 October 2026.

  • By 2 November: the fourteen days run out. One neighbour has consented in writing; the other has not replied, so a dispute is deemed to have arisen on that side.
  • November: your client appoints a surveyor, and the silent neighbour appoints one or agrees to share it. The surveyors inspect and draft the award.
  • 19 December: the earliest date the two-month notice period allows work to start, with consent or an award in place.
  • First week of January: the start date holds only if the award is agreed by then. If it is not, the start moves, and nothing in the Act lets you make it up.

Served in mid-November instead, the same notices would put the earliest lawful start in mid-January before the neighbours had said a word. So the quote date and the notice date are the same conversation.

The work that usually needs no notice

Some work “may all be too minor to require a notice”, according to the booklet. Its examples are drilling into a party wall “to fix plugs and screws for ordinary wall units or shelving”, cutting in for recessed wiring and sockets, and replastering. That is guidance, not an exemption in the Act, so a job that goes beyond it is back inside the notice rules.

What the Act does not do

When a client says they have planning, so they are fine, this is the part to walk them through. The Act does not replace other consents. The booklet says that even with planning permission or Building Control approval, owners “should still go through the proper procedures” under the Act. It does not make failing to serve a notice a crime. The booklet says “The Act contains no enforcement procedures for failure to serve a notice”. It also warns that neighbours “may seek to stop your work through a court injunction”. An injunction stops the whole site, and your programme with it.

Under section 7, the building owner must compensate the neighbour “for any loss or damage which may result” from the work. They must also not cause unnecessary inconvenience. The neighbour can also ask for security for expenses under section 12. The Act extends to England and Wales only; it does not apply in Scotland or Northern Ireland.

Two questions before you give a start date

Does this job cut into, raise or underpin a wall shared with a neighbour, build on the boundary, or dig within three or six metres of their foundations? If so, a notice is needed, and your client serves it.

Has that notice gone, or will it go, one or two months before the date you are about to promise? And does the programme leave the neighbour fourteen days to answer? If not, the date you give is a hope, not a start date.

ON THE START DATE YOU PROMISE AT THE QUOTE

The start date is only as firm as the date the notice went out.

Two months of notice and fourteen days of silence sit between a signed quote and the first steel. SendWork keeps the quote, the job and its dates on one record, so the day the notice was served and the day the award arrived are on the job, not in a text thread.